Data centres now use 5% of Dutch electricity, CBS says

According to the CBS data, approximately 200 data centres across the country were supplied with a total of 5,664 gigawatt-hours (GWh) of electricity in 2025. This represents an increase of roughly 12% compared to the previous year, highlighting an accelerating trajectory in power demand that shows no immediate signs of slowing down.

A closer examination of the figures reveals that the vast majority of this energy consumption is concentrated within a remarkably small number of massive facilities. Around 50 major data centres accounted for 5,289 GWh, or 93% of the national total. This volume is four times greater than what this elite tier of large facilities consumed in 2017. Interestingly, this dramatic quadrupling in power usage has occurred even though the total number of large-scale data centres operating in the Netherlands has remained relatively stable over the same period.

On an international scale, the Netherlands occupies a prominent position in the European digital landscape. Within the European Union, only Ireland utilizes a larger share of its national electricity supply to power data centres. According to Eurostat figures for 2024, Ireland led the bloc with an extraordinary 21.3% of its national electricity dedicated to data storage and processing facilities. The Netherlands followed at 4.6%, while Germany stood at 4.2%. In absolute terms of total energy volume consumed by these facilities, the Netherlands ranks third across the EU, trailing behind economic powerhouses Germany and Ireland.

The official national statistics compiled by CBS do not capture the entirety of the sector’s energy footprint. The totals explicitly exclude smaller, decentralized operations run by organizations such as universities, research institutions, and hospitals that maintain their own internal data facilities. The CBS estimates that these institutional and localized servers consumed an additional 142 GWh of electricity last year, further underscoring the pervasive integration of digital data management throughout Dutch society.

These environmental and energy statistics arrive against a backdrop of intensifying civil unrest and political debate regarding the rapid proliferation of massive tech facilities on Dutch soil. Less than two weeks prior to the release of the CBS report, climate and social justice activists occupied the active construction site of a controversial new data centre located in Amsterdam’s Westpoort district. The facility, slated to be leased to technology giant Microsoft once completed, became the focal point of coordinated protests organized by the climate action group Geef Tegengas, with active participation from Extinction Rebellion. The demonstration ultimately concluded with local law enforcement clearing the premises and removing the activists from the building site.

The project at the center of the controversy is a massive, one billion euro, 78-megawatt campus currently being developed by real estate developer Pure DC. According to investigative reporting by the Dutch newspaper NRC, the facility is projected to consume as much electricity in a single year as the entire city of Amsterdam. This staggering energy requirement has fueled fierce opposition from local residents, environmentalists, and urban planners alike.

Critics of the project argue that the development successfully circumvents a strict national ban on hyperscale data centres that was enacted by the Dutch government in 2022. The developers and planners managed to navigate the regulatory restrictions by structuring the project on paper as three distinct, smaller facilities rather than a single unified hyperscale campus, a maneuver that has drawn sharp criticism from lawmakers and civic organizations concerned about the country’s energy transition goals and grid capacity.

At the time of the protests and the subsequent police intervention, Microsoft issued a public statement addressing the escalating tensions surrounding the Westpoort development. The technology company stated that it fully understood the project "stirs up strong emotions" among the public and emphasized that it respected the democratic right of citizens to engage in peaceful protest. However, the friction between corporate digital expansion and local resource management remains a deeply contentious issue as the Netherlands grapples with the dual pressures of technological modernization and strict climate targets.